71、
Any one or any group of activities utilizing resources to transfer input into output can be viewed as a( ).
A、system
B、structure
C、procedure
D、process
72、
The process control charts are used( ).
A、to graph what typically focuses on the prevention of a problem
B、to detect the problem
C、to reject the problem
D、to determine the acceptability of the sample
73、
The IT service manager has learned that a software can improve the efficiency of current and future project tasks. Because the software is fresh to the Company. The engineer is not familiar with the software. The IT service manager decides to send the highest level engineer to attend the external training course. The project manager uses( )risk strategies.
A、mitigation
B、enhancement
C、development
D、sharing
74、
( )is closet to Deming's definition of Quality.
A、Conformance to requirements
B、Fitness for use
C、Continuous improvement of products and services
D、Customer focus
75、
The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternative new manager, the team is opposed to the comments from the new manager. The team is at( )development stages.
A、Forming
B、Storming
C、Norming
D、Performing
2026上半年真題哪里看?
微信掃碼看真題+估分
▼ ▼ ▼
熱門:系統集成項目管理工程師備考 | 網絡工程師備考 | 軟件設計師備考
推薦:系統規劃與管理師網絡課堂 | 2026年軟考報名時間及入口匯總表
活動:資料下載 | 新人禮包 | 2026上半年軟考真題估分![]()
課程:系統規劃與管理師備考策略 | PMP課程
軟考備考資料免費領取
去領取
專注在線職業教育25年